Facility Also to House 3 MW Biogas to Grid AD Plant : £150m EPC Contract for 28 MW Waste to Energy Gasification Plant in Hull
Stuttgart based engineering firm, M+W Group, has been named as the main Engineering, Procurement and Construction (EPC) contractor for the delivery of a new waste to energy plant in Hull, UK which will incorporate fluidised bed gasification, anaerobic digestion and solar PV technologies.
The company said that the new Energy Works waste to energy plant is designed to reduce the need to for local landfill as well as relying on fossil fuel generated power to meet local energy demand.
Once operational the plant is expected to be able to generate up to 28MW of electricity, or which around 25 MW will be exported to the grid with 3 MW being used for parasitic load. In addition, a second phase of the development will see the construction of an anaerobic digestion plant that will inject the equivalent of 3 MWt of renewable biogas directly into the national grid. The solar panels will generate around 36 kW of electricity.
Located in the industrial heart of the city, the facility will see the redevelopment of two adjacent brownfield sites covering an area of 12 acres. According to the German contractor, to reduce the need for vehicular transportation and impact of any congestion in the area during the construction and operation of the facility, a special high-line conveyor and access route will be created to connect the two sites.
The engineering firm added that another key feature of the development is the promotion of a better understanding of how new technologies and techniques can transform the way waste is managed. This includes, for example, the latest methods of recycling and the use of alternative fuels to produce sustainable energy.
With this in mind, the new facility incorporates an educational “Energy Academy”, providing modern research and development facilities in collaboration with local Hull University.
Working on the project alongside M+W Group will be two main sub-contractors; Outotec, an international specialist in advanced gasification technology; and Spencer Group, the Hull-based engineering and construction business leading the civil engineering works for the new facility.
Finance
As an advanced conversion technology (ACT), this project qualified for a Contract For Difference (CFD) with a strike price of £119.89 (2014 price). This subsidy will be grandfathered for 15 years ensuring long-term renewable energy production and recycling.
In March 2013 year the company secured a £19.9 million grant from the European Regional Development Fund (ERDF) for the project. (See WMW story)
Construction is due to start in January 2016 with completion scheduled for summer 2017.
Read More
JV Preferred Bidder for 25 MW Waste to Energy Gasification Plant in Hull
Energy Works, which is developing a facility in Hull that will combine a 25 MW waste gasification plant, has selected a joint venture as preferred bidder to design, build and operate the facility.
VIDEO: CDM Project Brings Biogas Fuelled Cooking to Nepalese HouseholdsA Clean Development Mechanism (CDM) programme to bring clean-burning cooking stoves fuelled by biogas from the anaerobic digestion of animal wastes to households in is improving health for people in Nepal.
Vienna University Opens Twin Fluidised Bed Waste Gasification Test Plant
In Austria the University of Vienna has opened a new test facility as part of its on going research into the use of a twin fluidised bed gasification process to recover high value fuels and gases from wastes.